ORNAMENTAL METAL FENCING SYSTEM
Aegis II - Majestic 2-Rail or 3-Rail Style
Construction Specifications
Section 02830
AEGIS II - MAJESTIC 2-RAIL OR 3-RAIL STYLE
PART 1 - GENERAL
1.01 WORK INCLUDED
The contractor shall provide all labor, materials, and appurtenances necessary for
installation of the ornamental metal fencing system defined herein at (specify project
site).
1.02 RELATED WORK
Section _____ _____ - Earthwork
Section _____ _____ - Concrete
1.03 SYSTEM DESCRIPTION
The manufacturer shall supply a total ornamental metal fencing system of the Majestic
design. The system shall include all components (i.e., pickets, rails, posts, gates and
hardware) required.
1.04 QUALITY ASSURANCE
The contractor shall provide laborers and supervisors who are thoroughly familiar with
the type of construction involved and materials and techniques specified.
1.05 REFERENCES
ASTM A526-Steel Sheet Zinc-Coated (Galvanized by the Hot Dip Process)
ASTM B117-Salt Spray Testing
1.06 SUBMITTAL
The manufacturer's literature shall be submitted prior to installation.
1.07 PRODUCT HANDLING AND STORAGE
Upon receipt at the job site, all materials shall be checked to ensure that no damage
occurred during shipping or handling. Materials shall be stored in such a manner to ensure
proper ventilation and drainage, and to protect against damage, weather, vandalism, and
theft.
PART 2 - MATERIALS
2.01 MANUFACTURER
The ornamental metal fencing system shall conform to AEGIS II, Majestic 2-Rail or
3-Rail style manufactured by Ameristar Fence Products, Inc., in Tulsa, Oklahoma.
2.02 MATERIAL
A. The materials for fence framework (i.e., pickets, rails, and posts) shall be
manufactured from coil steel having a minimum yield strength of 50,000 psi. The steel
shall be galvanized to meet the requirements of ASTM A526 with a minimum zinc coating
weight of .90 ounces per square foot (coating Designation G-90), hot-dip process.
Galvanized framework shall be subject to a six stage pretreatment/wash (with zinc
phosphate) followed by "PERMACOAT", an
electrostatic spray application of a two coat powder system. The base coat is a
thermosetting epoxy powder coating (gray in color) with a minimum thickness of 2-4
mils. The top coat is a "no-mar" TGIC polyester powder coat finish with a
minimum thickness of 2-4 mils. The color shall be (specify black, brown, white, or desert
sand). Coated galvanized framework shall have a salt spray resistance of 3,500 hours
using ASTM B117 without loss of adhesion.
B. Material for fence pickets shall be 1" square x 16ga. tubing. The
cross-sectional shape of the rails shall conform to the manufacturer's Forerunner design with outside cross-section dimensions of 1.75" square
and a minimum thickness of 14ga. Post spacing shall be (specify 71-1/4" for 6' o.c.
nominal or 96" for 8' o.c. nominal with 2-1/2" square posts). Picket holes in
the Forerunner rail shall be spaced 4.98" o.c. Picket retaining rods shall be
0.125" dia. galvanized steel. Posts shall be a minimum of 2-1/2" square x 12ga.
Rubber grommets shall be supplied to seal all picket-to-rail intersections.
2.03 FABRICATION
A. Pickets, rails, and posts shall be precut to specified lengths. Forerunner
rails shall be pre-punched to accept pickets.
B. Grommets shall be inserted into the pre-punched holes in the rails and pickets
shall be inserted through the grommets so that pre-drilled picket holes align with the
internal upper raceway of the Forerunner rails (Note: This can best be accomplished
by making an alignment jig). Retaining rods shall be inserted into each Forerunner
rail so that they pass through the predrilled holes in each picket.
C. Completed sections (i.e., panels) shall be capable of supporting a 600 lb. load
applied at midspan without permanent deformation. Panels shall be biasable to a 25% change
in grade.
D. Gates shall be fabricated using AEGIS II panel material and gate ends
having the same outside cross-section dimensions as the Forerunner rail. Each
upright and rail intersection shall be joined by welding. Each picket and rail
intersection shall also be joined by welding.
PART 3 - EXECUTION
3.01 PREPARATION
All new installation shall be laid out by the contractor in accordance with the
construction plans.
3.02 INSTALLATION
Fence posts shall be set at spacings of either 71-1/4" or 8' o.c. plus or minus
1/2", depending on the span specified. Gate posts shall be spaced according to the
gate openings specified in the construction plans. The "Earthwork" and
"Concrete" sections of this specification shall govern post base placement and
material requirements. AEGIS II panels shall be attached to posts using panel
brackets supplied by the bolt-on hardware supplied by manufacturer.
3.03 CLEANING
The contractor shall clean the jobsite of excess materials; post hole excavations
shall be scattered uniformly away from posts.
AEGIS II - CLASSIC 2-RAIL OR 3-RAIL STYLE
PART 1 - GENERAL
1.01 WORK INCLUDED
The contractor shall provide all labor, materials, and appurtenances necessary for
installation of the ornamental metal fencing system defined herein at (specify project
site).
1.02 RELATED WORK
Section _____ _____ - Earthwork
Section _____ _____ - Concrete
1.03 SYSTEM DESCRIPTION
The manufacturer shall supply a total ornamental metal fencing system of the Classic
design. The system shall include all components (i.e., pickets, rails, posts, gates and
hardware) required.
1.04 QUALITY ASSURANCE
The contractor shall provide laborers and supervisors who are thoroughly familiar with
the type of construction involved and materials and techniques specified.
1.05 REFERENCES
ASTM A526-Steel Sheet Zinc-Coated (Galvanized by the Hot Dip Process)
ASTM B117-Salt Spray Testing
1.06 SUBMITTAL
The manufacturer's literature shall be submitted prior to installation.
1.07 PRODUCT HANDLING AND STORAGE
Upon receipt at the job site, all materials shall be checked to ensure that no damage
occurred during shipping or handling. Materials shall be stored in such a manner to ensure
proper ventilation and drainage, and to protect against damage, weather, vandalism, and
theft.
PART 2 - MATERIALS
2.01 MANUFACTURER
The ornamental metal fencing system shall conform to AEGIS II, Classic 2-Rail or
3-Rail style manufactured by Ameristar Fence Products, Inc., in Tulsa, Oklahoma.
2.02 MATERIAL
A. The materials for fence framework (i.e., pickets, rails, and posts) shall be
manufactured from coil steel having a minimum yield strength of 50,000 psi. The steel
shall be galvanized to meet the requirements of ASTM A526 with a minimum zinc coating
weight of .90 ounces per square foot (coating Designation G-90), hot-dip process.
Galvanized framework shall be subject to a six stage pretreatment/wash (with zinc
phosphate) followed by "PERMACOAT", an electrostatic spray application of a two coat powder system. The
base coat is a thermosetting epoxy powder coating (gray in color) with a minimum
thickness of 2-4 mils. The top coat is a "no-mar" TGIC polyester powder
coat finish with a minimum thickness of 2-4 mils. The color shall be (specify black,
brown, white, or desert sand). Coated galvanized framework shall have a salt spray
resistance of 3,500 hours using ASTM B117 without loss of adhesion.
B. Material for fence pickets shall be 1" square x 16ga. tubing. The
cross-sectional shape of the rails shall conform to the manufacturer's Forerunner design with outside cross-section dimensions of
1.75" square and a minimum thickness of 14ga. Post spacing shall be (specify
71-1/4" for 6' o.c. nominal or 96" for 8' o.c. nominal with 2-1/2" square
posts). Picket holes in the Forerunner rail shall be spaced 4.98" o.c. Picket
retaining rods shall be 0.125" dia. galvanized steel. Posts shall be a minimum of
2-1/2" square x 12ga. Rubber grommets shall be supplied to seal all picket-to-rail
intersections.
2.03 FABRICATION
A. Pickets, rails, and posts shall be precut to specified lengths. Forerunner
rails shall be pre-punched to accept pickets.
B. Grommets shall be inserted into the pre-punched holes in the rails and pickets
shall be inserted through the grommets so that pre-drilled picket holes align with the
internal upper raceway of the Forerunner rails (Note: This can best be accomplished
by making an alignment jig). Retaining rods shall be inserted into each Forerunner
rail so that they pass through the predrilled holes in each picket.
C. Completed sections (i.e., panels) shall be capable of supporting a 600 lb. load
applied at midspan without permanent deformation. Panels shall be biasable to a 25% change
in grade.
D. Gates shall be fabricated using AEGIS II panel material and gate ends
having the same outside cross-section dimensions as the Forerunner rail. Each
upright and rail intersection shall be joined by welding. Each picket and rail
intersection shall also be joined by welding.
PART 3 - EXECUTION
3.01 PREPARATION
All new installation shall be laid out by the contractor in accordance with the
construction plans.
3.02 INSTALLATION
Fence posts shall be set at spacings of either 71-1/4" or 8' o.c. plus or minus
1/2", depending on the span specified. Gate posts shall be spaced according to the
gate openings specified in the construction plans. The "Earthwork" and
"Concrete" sections of this specification shall govern post base placement and
material requirements. AEGIS II panels shall be attached to posts using panel
brackets supplied by the bolt-on hardware supplied by manufacturer.
3.03 CLEANING
The contractor shall clean the jobsite of excess materials; post hole excavations
shall be scattered uniformly away from posts.